Mold Remediation in Mission Viejo, CA
Rain water seeping through the roof making its way into the patioArea(s) affected: Add-on room patio onlyBuilding materials affected: Ceiling and wallsScope of work: Day #1 – Prior to the start of work, the homeowner is going to schedule their electrician to disconnect power to ceiling fans and possibly remove lights as well. We will manipulate contents by relocating furniture into the house. Day #2 – Start on demolition from top to bottom. We will start on the ceiling and work our way down.Day #3 – Continue with the demolition of all walls, windows and last but not least the tile must be broken andswept up to expose the slab.Day #4 – Make sure the jobsite is clean and make sure any of the bushes or grass areas areclean from any debris.