Water Damage in Paramount , CA ,
The project involved responding to a water and mold-affected area in the entry closet, HVAC closet, hallway, and adjacent spaces. After initial inspection and asbestos testing confirmed non-detect results, the crew proceeded with demolition of affected drywall, laminate flooring, insulation, carpet/padding, and baseboards. Containment was built, HEPA vacuuming and antimicrobial cleaning were performed, framing was sanded and treated, cavities were sealed, and equipment was set up for drying and air scrubbing. The team returned to complete prep work, change HEPA filters, clean all surfaces, and ensure the site was fully ready for clearance testing, which later passed. Final on-site tasks included removing containment, picking up equipment, and inspecting the area for repair needs.