Water Damage Repair in Los Angeles , CA
On 1/21/25, the team met with the manager and maintenance staff, explained the work process, and received approval from Benjamin to proceed. Containment and floor protection were set up, contents were moved, and drywall removal began. Secondary damage and mold growth were found, requiring a change order for additional work. On 1/29/25, the remaining affected drywall was removed, framing was HEPA vacuumed and wet wiped, and containment was set up for clearance preparation. Later, containment and equipment were removed, and the project was marked ready for repairs.